Wednesday, June 7, 2017

District 131 summer maintenance and improvement projects scheduled

As the school year draws to a close, East Aurora School District 131 will take the opportunity to maintain and improve many of its school buildings.

In addition to the high school construction which continues on-schedule, several school buildings have work scheduled to be completed this summer. Projects include roofing, asphalt and patching, entry improvements, window replacement, masonry tuck-pointing, as well as interior improvements.

Estimated project dates, schools, projects and notes are listed below, as supplied by contractor Cordogan Clark. Estimated start and target completion dates are subject to change, due to weather and unforeseen conditions.

Dates (approximate) School Project
June 7-30 Krug Roofing
June 7-30 Oak Park Roofing
June 7-30 Cowherd MS Roofing
June 8-30 Hermes Roofing
June 8-30 Gates Roofing
July 5-21 Allen Roofing
July 5-28 Johnson Roofing
July 5-31 Waldo MS Roofing
July 5-31 Simmons MS Roofing

Project notes: Tar used on roofing projects may produce an unpleasant but harmless odor.

 

Dates (approximate) School Project
June 12-16 Multi-site* Asphalt patching
July 5-28 Gates Asphalt
July 5-28 Johnson Asphalt
July 5-28 Hermes Asphalt

Project notes: Parking lot access may be altered during pavement projects.
*Patching work will be performed at Allen, Bardwell, Beaupre, Brady, Cowherd MS, Dieterich, Magnet Academy, B&G, Krug, O'Donnell, Rollins and Simmons MS.

 

Dates (approximate) School Project
June 7-31 Brady Entry improvements
June 7-31 Waldo MS Entry improvements
July 11-31 Dieterich Interior improvements
July 11-31 Gates Interior improvements
June 26-July 10 Dieterich/Gates Abatement

Project notes: Student entrances during these projects may be altered and have been coordinated with the schools. Interior improvements include gym ceiling and lighting renovation. Areas have been coordinated with school administration to prevent occupancy. Abatement areas will be segregated from any occupants to prevent exposure.

 

Dates (approximate) School Project
June 26-July 10 Oak Park/Gates Abatement
July 5-31 Oak Park Window replacement
July 5-31 Gates Window replacement

Project notes: Abatement areas will be segregated from any occupants to prevent exposure.

 

Dates (approximate) School Project
June 7-July 31 Waldo MS Masonry tuck-pointing
July 5-July 28 Magnet Academy Masonry tuck-pointing

Project notes: Masonry tuck-pointing will create noise and dust at times in the surrounding areas

 

Dates (approximate) School Project
July 7-August 18 Waldo MS Science rooms
July 7-August 18 Simmons MS Science rooms

Project notes: Interior science lab renovations; minimal impact on surrounding areas.

 

Dates (approximate) School Project
June 7-July 14 Allen Mechanical improvements
June 7-July 14 Bardwell Mechanical improvements
June 7-July 14 Child Service Center Mechanical improvements
June 7-July 14 Oak Park Mechanical improvements
June 12-July 28 Simmons MS Mechanical improvements

Project notes: air conditioning may be disrupted in certain areas

 

Posted on 6/7/2017
Last updated by Justin Skattum on 6/16/2017 7:01 AM


Broadcast Email Preview

Enter a valid email address, and click the "Preview" button to send a preview of this news item to the address you specify.

Email Address:


      News & Information

About Us

Attendance
Phone Numbers

Boundary Maps

Building Rental
Forms

Community Email
Sign Up

District Finances

Emergency School
Closings

Enlightener

Freedom of
Information Act

News & Information

Parent & Student
Portal

Photo Gallery

Report Cards

Service Centers

Staff Directory

Union Officials